SupERB- Progress and Implementation
||
During the Interim Period (December 2018-May 2020) of the Project the following milestones were achieved: Completed Work-Packages (WP): WP3, “Investigation of mechanical and thermal properties of available materials” and WP4, “Establishment of criteria for target performance level”, were successfully completed....
continue reading
SupERB-Mid-Term-meeting
SupERB Interim Meeting, 23/06/2020
||
The due date of the Interim Meeting of SupERB coincided with the unprecedented coronavirus pandemic (COVID-19). Because of imposed restrictions and precautions measures, it was held online on June 23th, 2020 using the Skype platform. The online meeting was hosted...
continue reading
SupERB Kick-off Meeting, 11/01/2019
||
The kick-off meeting of SupERB was successfully held in Limassol, Cyprus on January 11th, 2019 with the participation of the project’s partners and the designated RPF scientific officer. During the meeting, members of the HO research team gave presentations on...